IGF::OT::IGF THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF THE FOLLOWING: LAYOUT AND INSTALL PIPING FOR CONNECTION OF WATER TREATMENT UNIT VERIFY EXISTING CONDITIONS IN

Awarded to TRI-TECHNIC INC

PIID NNA15BB51TUS · USAspendingConstruction
$44.8K
Data last updated Oct 22, 2026 · Source: USAspending
Transaction obligation$44,798sum disclosed on award record
Current contract valueNot reportednot interchangeable with obligation
Potential contract valueNot reportedincluding options if reported
Award dateMar 24, 2016
Company legal name
TRI-TECHNIC INC
UEI / CAGE
JFLYJKT6N2L5 / Not reported
Parent award
Not reported
Awarding agency
National Aeronautics and Space Administration
Subagency
National Aeronautics and Space Administration
Industry
Construction
NAICS
236220
PSC
Y1JZ
Performance period
Not reported — Not reported
Recipient address
185 S FAIRVIEW LN, SONORA, TUOLUMNE, CA, 95370
Place of performance
MOFFETT FIELD, SANTA CLARA, CA, 94035
Source last modified
Oct 21, 2026

Description

IGF::OT::IGF THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF THE FOLLOWING: LAYOUT AND INSTALL PIPING FOR CONNECTION OF WATER TREATMENT UNIT VERIFY EXISTING CONDITIONS IN THE AREA OF WORK PROVIDE ELECTRIC POWER FOR MECHANICAL EQUIPMENT ANCHOR WATER TREATMENT EQUIPMENT INSTALL AND ASSEMBLE WATER TREATMENT SYSTEM PROTECT RAISED FLOOR AND OTHER EXISTING FINISHES COORDINATE WORK SCHEDULE WITH CONTRACTING OFFICER REPRESENTATIVE (COR) AND BUILDING USER PROVIDE PUMPS WITH SPECIFIED WATER FLOW TEST QUALITY CRITERIA FROM WATER TREATMENT SYSTEM FOR COMPONENTS LISTED IN THE D-WAVE COMPUTER WATER QUALITY CRITERIA, AS NOTED IN THE DWGS. SUBMIT WATER QUALITY LAB REPORT FOR REVIEW COMMISSION TREATMENT SYSTEM KEEP DUST TO MINIMUM AND CLEAN UP EACH DAY. PERFORM FUNCTIONAL TEST BY APPROVED THIRD PARTY INDEPENDENT TEST AND BALANCING AGENCY PLAN WORK AND PERFORM WORK WITH EXTRA CAUTION TO AVOID ANY INTERRUPTION TO THE OPERATION OF THE QUANTUM COMPUTER. COMMUNICATE ALL WORK TASK AND SCHEDULES TO THE COR COMPLY WITH ALL SAFETY REQUIREMENTS SUBMIT SAFETY PLAN, WORK PLAN, COMMISSIONING PLAN, PROGRAMMING, FIELD TEST REPORTS, INTEGRATED SYSTEM TEST REPORT, VALIDATION REPORT, AND AS-BUILT DOCUMENTATION TO COR. FOR MORE INFORMATION SEE ATTACHED PERFORMANCE SCOPE OF WORK, DRAWINGS, AND ATTACHMENTS

View federal source ↗

Derived from official transactions

Contract lifecycle

  1. Contract modified

    IGF::OT::IGF THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF THE FOLLOWING: LAYOUT AND INSTALL PIPING FOR CONNECTION OF WATER TREATMENT UNIT VERIFY EXISTING CONDITIONS IN

    US · usaspendingSource ↗
  2. Value increased

    IGF::OT::IGF THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF THE FOLLOWING: LAYOUT AND INSTALL PIPING FOR CONNECTION OF WATER TREATMENT UNIT VERIFY EXISTING CONDITIONS IN

    US · usaspending$3.8KSource ↗
  3. Award announced

    IGF::OT::IGF D-WAVE WATER FILTRATION SYSTEM FOR Q-COMPUTER, N258 THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF THE FOLLOWING: LAYOUT AND INSTALL PIPING FOR CONNECTION OF

    US · usaspendingSource ↗
  4. Value increased

    IGF::OT::IGF D-WAVE WATER FILTRATION SYSTEM FOR Q-COMPUTER, N258 THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF THE FOLLOWING: LAYOUT AND INSTALL PIPING FOR CONNECTION OF

    US · usaspending$41KSource ↗

Point-in-time model

Contract change outlook

Predictive intelligenceInsufficient historyNo eligible point-in-time model has produced a prediction for this record.

Uncollapsed source history

Transactions and modifications

Action dateModificationAction typeExact obligationCurrent totalPotential totalDescriptionSource
Mar 24, 20165D$3,808.00Not reportedNot reportedIGF::OT::IGF THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF THE FOLLOWING: LAYOUT AND INSTALL PIPING FOR CONNECTION OF WATER TREATMENT UNIT VERIFY EXISTING CONDITIONS IN THE AREA OF WORK PROVIDE ELECTRIC POWER FOR MECHANICAL EQUIPMENT ANCHOR WATER TREATMENT EQUIPMENT INSTALL AND ASSEMBLE WATER TREATMENT SYSTEM PROTECT RAISED FLOOR AND OTHER EXISTING FINISHES COORDINATE WORK SCHEDULE WITH CONTRACTING OFFICER REPRESENTATIVE (COR) AND BUILDING USER PROVIDE PUMPS WITH SPECIFIED WATER FLOW TEST QUALITY CRITERIA FROM WATER TREATMENT SYSTEM FOR COMPONENTS LISTED IN THE D-WAVE COMPUTER WATER QUALITY CRITERIA, AS NOTED IN THE DWGS. SUBMIT WATER QUALITY LAB REPORT FOR REVIEW COMMISSION TREATMENT SYSTEM KEEP DUST TO MINIMUM AND CLEAN UP EACH DAY. PERFORM FUNCTIONAL TEST BY APPROVED THIRD PARTY INDEPENDENT TEST AND BALANCING AGENCY PLAN WORK AND PERFORM WORK WITH EXTRA CAUTION TO AVOID ANY INTERRUPTION TO THE OPERATION OF THE QUANTUM COMPUTER. COMMUNICATE ALL WORK TASK AND SCHEDULES TO THE COR COMPLY WITH ALL SAFETY REQUIREMENTS SUBMIT SAFETY PLAN, WORK PLAN, COMMISSIONING PLAN, PROGRAMMING, FIELD TEST REPORTS, INTEGRATED SYSTEM TEST REPORT, VALIDATION REPORT, AND AS-BUILT DOCUMENTATION TO COR. FOR MORE INFORMATION SEE ATTACHED PERFORMANCE SCOPE OF WORK, DRAWINGS, AND ATTACHMENTSUSAspending ↗
Jun 26, 20150Not reported$40,990.00Not reportedNot reportedIGF::OT::IGF D-WAVE WATER FILTRATION SYSTEM FOR Q-COMPUTER, N258 THE WORK TO BE PERFORMED UNDER THIS PROJECT CONSISTS OF THE FOLLOWING: LAYOUT AND INSTALL PIPING FOR CONNECTION OF WATER TREATMENT UNIT; VERIFY EXISTING CONDITIONS IN THE AREA OF WORK; PROVIDE ELECTRIC POWER FOR MECHANICAL EQUIPMENT; ANCHOR WATER TREATMENT EQUIPMENT; INSTALL AND ASSEMBLE WATER TREATMENT SYSTEM; PROTECT RAISED FLOOR AND OTHER EXISTING FINISHES.USAspending ↗