PROJECT NP-BLRI 1M20 THE PROJECT CONSISTS OF INSTALLING A DRAINAGE SYSTEM, REPLACEMENT OF ASPHALT CONCRETE PAVEMENT, INSTALLATION OF LIGHTWEIGHT CONCRETE SLAB, REPLACING BRIDGE SID

Awarded to OLYMPUS PAINTING CONTRACTORS INC

PIID 693C7321C000011US · USAspendingTransportation & Logistics
$3.8M
Data last updated Oct 22, 2026 · Source: USAspending
Transaction obligation$3,808,458sum disclosed on award record
Current contract valueNot reportednot interchangeable with obligation
Potential contract valueNot reportedincluding options if reported
Award dateFeb 25, 2021
Company legal name
OLYMPUS PAINTING CONTRACTORS INC
UEI / CAGE
Z87XLJ5AEXK2 / Not reported
Parent award
Not reported
Awarding agency
Department of Transportation
Subagency
Federal Highway Administration
Industry
Transportation & Logistics
NAICS
237310
PSC
Y1LB
Performance period
Not reported — Not reported
Recipient address
556 ANCLOTE RD, TARPON SPRINGS, PINELLAS, FL, 34689
Place of performance
ROANOKE, ROANOKE CITY, VA, 24001
Source last modified
Nov 3, 2026

Description

PROJECT NP-BLRI 1M20 THE PROJECT CONSISTS OF INSTALLING A DRAINAGE SYSTEM, REPLACEMENT OF ASPHALT CONCRETE PAVEMENT, INSTALLATION OF LIGHTWEIGHT CONCRETE SLAB, REPLACING BRIDGE SIDEWALK, REPLACING AND RESETTING BRIDGE CURB, REPLACING STONE MASONRY A

View federal source ↗

Derived from official transactions

Contract lifecycle

  1. Award announced

    PROJECT NP-BLRI 1M20 THE PROJECT CONSISTS OF INSTALLING A DRAINAGE SYSTEM, REPLACEMENT OF ASPHALT CONCRETE PAVEMENT, INSTALLATION OF LIGHTWEIGHT CONCRETE SLAB, REPLACING BRIDGE SID

    US · usaspendingSource ↗
  2. Value increased

    PROJECT NP-BLRI 1M20 THE PROJECT CONSISTS OF INSTALLING A DRAINAGE SYSTEM, REPLACEMENT OF ASPHALT CONCRETE PAVEMENT, INSTALLATION OF LIGHTWEIGHT CONCRETE SLAB, REPLACING BRIDGE SID

    US · usaspending$3.8MSource ↗

Point-in-time model

Contract change outlook

Predictive intelligenceInsufficient historyNo eligible point-in-time model has produced a prediction for this record.

Uncollapsed source history

Transactions and modifications

Action dateModificationAction typeExact obligationCurrent totalPotential totalDescriptionSource
Feb 25, 20210Not reported$3,808,457.50Not reportedNot reportedPROJECT NP-BLRI 1M20 THE PROJECT CONSISTS OF INSTALLING A DRAINAGE SYSTEM, REPLACEMENT OF ASPHALT CONCRETE PAVEMENT, INSTALLATION OF LIGHTWEIGHT CONCRETE SLAB, REPLACING BRIDGE SIDEWALK, REPLACING AND RESETTING BRIDGE CURB, REPLACING STONE MASONRY AUSAspending ↗