FIRMQUARRYResearch workspace

GOVERNMENT CONTRACT / DELIVERY ORDER

ADDITIONAL DESIGN WORK FOR ADDITIONAL OFFICE SQUARE FOOTAGE, A SEPTIC SYSTEM, AND A WELL PUMPHOUSE TO THE CURRENT DESIGN FOR THE NEW HEADQUARTERS BUILDING.

Awarded to JACKOLA ENGINEERING & ARCHITECTURE PC

PIID 140FC124F0034US · USAspendingOther
$75.2K
Data last updated Oct 22, 2026 · Source: USAspending
Transaction obligation$75,173sum disclosed on award record
Current contract valueNot reportednot interchangeable with obligation
Potential contract valueNot reportedincluding options if reported
Award dateSep 5, 2024
Company legal name
JACKOLA ENGINEERING & ARCHITECTURE PC
UEI / CAGE
XPA7TJ5WV4B3 / Not reported
Parent award
Not reported
Awarding agency
Department of the Interior
Subagency
U.S. Fish and Wildlife Service
Industry
Other
NAICS
541330
PSC
C211
Performance period
Not reported — Not reported
Recipient address
2250 US HIGHWAY 93 S, KALISPELL, FLATHEAD, MT, 59901
Place of performance
CHARLO, LAKE, MT, 59824
Source last modified
Oct 23, 2026

Description

ADDITIONAL DESIGN WORK FOR ADDITIONAL OFFICE SQUARE FOOTAGE, A SEPTIC SYSTEM, AND A WELL PUMPHOUSE TO THE CURRENT DESIGN FOR THE NEW HEADQUARTERS BUILDING.

View federal source ↗

Derived from official transactions

Contract lifecycle

  1. Award announced

    ADDITIONAL DESIGN WORK FOR ADDITIONAL OFFICE SQUARE FOOTAGE, A SEPTIC SYSTEM, AND A WELL PUMPHOUSE TO THE CURRENT DESIGN FOR THE NEW HEADQUARTERS BUILDING.

    US · usaspendingSource ↗
  2. Contract modified

    ADDITIONAL DESIGN WORK FOR ADDITIONAL OFFICE SQUARE FOOTAGE, A SEPTIC SYSTEM, AND A WELL PUMPHOUSE TO THE CURRENT DESIGN FOR THE NEW HEADQUARTERS BUILDING.

    US · usaspendingSource ↗
  3. Value increased

    ADDITIONAL DESIGN WORK FOR ADDITIONAL OFFICE SQUARE FOOTAGE, A SEPTIC SYSTEM, AND A WELL PUMPHOUSE TO THE CURRENT DESIGN FOR THE NEW HEADQUARTERS BUILDING.

    US · usaspending$75.2KSource ↗

Point-in-time model

Contract change outlook

Predictive intelligenceInsufficient historyNo eligible point-in-time model has produced a prediction for this record.

Uncollapsed source history

Transactions and modifications

Action dateModificationAction typeExact obligationCurrent totalPotential totalDescriptionSource
Jul 30, 2026P00004A$75,173.08Not reportedNot reportedADDITIONAL DESIGN WORK FOR ADDITIONAL OFFICE SQUARE FOOTAGE, A SEPTIC SYSTEM, AND A WELL PUMPHOUSE TO THE CURRENT DESIGN FOR THE NEW HEADQUARTERS BUILDING.USAspending ↗