IGF::OT::IGF. THE PURPOSE OF THIS MODIFICATION IS TO 1) DIRECT THE CONTRACTOR TO ADD TRANSPORT OF TWO PIECES OF EQUIPMENT FROM THEIR CURRENT LOCATION TO THE UVRI FACILITY. REMOVE

Department of Defense

Procedure CONT_AWD_0007_9700_HDTRA108D0008_9700CPV 541990Not reported
Not reported
Data last updated Oct 22, 2026 · Source: USAspending.gov
Buyer identifier
Not reported
Primary supplier
CH2M HILL, INC
Procurement method
Not reported
Tender deadline
Not reported
Contract period
Not reported — Not reported
Native value
Not reported
USD comparison
Not shown — no auditable FX observation
Official source
Open notice ↗

Description

IGF::OT::IGF. THE PURPOSE OF THIS MODIFICATION IS TO 1) DIRECT THE CONTRACTOR TO ADD TRANSPORT OF TWO PIECES OF EQUIPMENT FROM THEIR CURRENT LOCATION TO THE UVRI FACILITY. REMOVE THE REQUIREMENT TO 2) DELIVER AND INSTALL THE TWO PIECES AS OF EQUIPMENT AS DESCRIBED MODIFICATION 03. 3) INCORPORATE A REVISED STATEMENT OF WORK DATED JULY 8, 2015. 4) ADMINISTRATIVE CHANGES TO CLIN 0001 AND CLIN 0002 PRICING DETAIL QUANTITY. 5) ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED AND IN FULL FORCE AND EFFECT.

Suppliers

Official lifecycle

Process timeline

  1. Contract modified

    IGF::OT::IGF, PROFESSIONAL SERVICES OF EQUIPMENT PROCUREMENT IN UGANDA

    US · usaspendingSource ↗
  2. Value decreased

    IGF::OT::IGF, PROFESSIONAL SERVICES OF EQUIPMENT PROCUREMENT IN UGANDA

    US · usaspending-$44.2KSource ↗
  3. Contract modified

    IGF::OT::IGF. THE PURPOSE OF THIS MODIFICATION IS TO 1) DIRECT THE CONTRACTOR TO ADD TRANSPORT OF TWO PIECES OF EQUIPMENT FROM THEIR CURRENT LOCATION TO THE UVRI FACILITY. REMOVE

    US · usaspendingSource ↗
  4. Contract modified

    IGF:OT:IGF. THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE OF CLIN 0001 FROM 24 JANUARY 2014 TO 27 FEBRUARY 2015 TO 24 JANUARY 2014 TO 31 JULY 2015. EXTENS

    US · usaspendingSource ↗
  5. Contract modified

    THE PURPOSE OF THIS MODIFICATION IS DE-SCOPE EFFORT; INCORPORATE A REVISED STATEMENT OF WORK; EXTEND THE PERIOD OF PERFORMANCE OF CLIN 0001 THRU FEBRUARY 27, 2015.

    US · usaspendingSource ↗
  6. Value decreased

    THE PURPOSE OF THIS MODIFICATION IS DE-SCOPE EFFORT; INCORPORATE A REVISED STATEMENT OF WORK; EXTEND THE PERIOD OF PERFORMANCE OF CLIN 0001 THRU FEBRUARY 27, 2015.

    US · usaspending-$10.8KSource ↗
  7. Contract modified

    THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE PERIOD OF PERFORMANCE OF THE TASK ORDER FROM: JANUARY 24, 2014 TO OCTOBER 24, 2014. TO: JANUARY 24, 2014 TO NOVEMBER 24, 2014. THI

    US · usaspendingSource ↗
  8. Contract modified

    THE PURPOSE OF THIS MODIFICATION IS TO ADD REWIRING/VOLTAGE STABILIZER TO SUPPORT EQUIPMENT TO BE INSTALLED AT THE ARBOVIROLOGY SECTION OF THE UVRI FACILITY AND TO EXERCISE OPTION

    US · usaspendingSource ↗
  9. Value increased

    THE PURPOSE OF THIS MODIFICATION IS TO ADD REWIRING/VOLTAGE STABILIZER TO SUPPORT EQUIPMENT TO BE INSTALLED AT THE ARBOVIROLOGY SECTION OF THE UVRI FACILITY AND TO EXERCISE OPTION

    US · usaspending$264.1KSource ↗
  10. Option exercised

    THE PURPOSE OF THIS MODIFICATION IS TO ADD REWIRING/VOLTAGE STABILIZER TO SUPPORT EQUIPMENT TO BE INSTALLED AT THE ARBOVIROLOGY SECTION OF THE UVRI FACILITY AND TO EXERCISE OPTION

    US · usaspendingSource ↗
  11. Award announced

    CBEP UGANDA EQUIPMENT PROCUREMENT, INSTALLATION, CERTIFICATION AND TRAINING.

    US · usaspendingSource ↗
  12. Value increased

    CBEP UGANDA EQUIPMENT PROCUREMENT, INSTALLATION, CERTIFICATION AND TRAINING.

    US · usaspending$1.2MSource ↗

Auditable model output

Predictive intelligence

Predictive intelligenceInsufficient historyNo eligible point-in-time model has produced a prediction for this record.

Append-only source history

Source records

RecordDateStagesFetched